November 2024 (Update)

Slider is playing
A

October 2024 (Update)

Slider is playing
A

September 2024 (Update)

Slider is playing
A

July 2024 (Update)

Slider is playing
A

June 2024 (Update)

Slider is playing
A
Slider is playing
A

May 2024 (Update)

Slider is playing
A
Slider is playing
A

April 2024 (Update)

Slider is playing
A
Slider is playing
A

February 2024 (Update)

Slider is playing
2/14 Update A

January 2024 (Update)

Slider is playing
January Update

December 2023 (Update)

Slider is playing
Update A

November 2023 (Update)

Slider is playing
Update 1

October 2023 (Update)

Slider is playing
Update A

September 2023 (Summary)

High school building pad was completed, concrete footings placed, and a section of sidewalk replaced. Elementary school addition building pad and storm sewer installation is in progress.

On the horizon...

  • High School Addition

    • Under slab plumbing and electrical install

    • Concrete slab on grade placement

  • Elementary School Addition

    • Concrete footing placement

    • Under slab plumbing and electrical install

    • Concrete slab on grade placement

Slider is playing
Concrete footings in progress (September 14, 2023)

September 2023

Concrete removal and access road installation has gotten underway at NCEMS, while dirt work for the new addition at NCHS is complete and footings are being poured.

Slider is playing
NCEMS Access Road

August 2023

Parking & Traffic Flow at NCEMS

Slider is playing
NCEMS Parking & Traffic Flow Info 23-24

Parking & Traffic Flow at NCHS

NCHS Parking Map

USD 115 Event Parking

USD 115 Event Parking 23-24

June 2023

NC Bond Construction Outline

Bond Timeline

February 2023

The bond construction process continues to be in the meeting phases to gather input from staff.  The plans for phase 1, new classrooms for grade school and high school, are just about complete and will be submitted for bids soon. The approval of these bids should be at the June 12th board meeting and construction is set to begin in July. 

Meeting

Zach Snethen from HTK, Eric Stallbaumer with AHRS and Tucker Peddicord with Lighthouse Construction met with staff on February 7th to help finalize plans for the first phase of the construction process before they go out for bids. This was the 2nd meeting for the high school science teachers and the primary teachers from the grade school. The group also conducted their first meeting with high school art, band, office staff and special education for the remodeling phase at the high school. The staff input has been very valuable during pre-construction and the meetings will continue throughout the different construction phases. Plans will be shared with the board during their meeting February 13th.

December 2022

For the next few months, the construction for the bond will be in the planning stages. Shovels will hit the ground on June 1st and a great deal of planning will take place before that can happen.  Zach Snethen from HTK, Eric Stallbaumer with AHRS and Tucker Peddicord with Lighthouse Construction, met with administration, teachers, Amy Sudbeck #115 BOE and Steve Rothers to begin discussion on the layout of the classrooms and building infrastructure. Input will continue to be gathered so that bids can be requested and submitted. Survey crews have also been busy identifying underground lines. 

Staff from the Elementary discussing the Pre K, TK and Kindergarten classrooms. 

NCEMS Dec 2022

High School science teachers giving their input about the new classrooms. 

NCHS Dec 2022