November 2024 (Update)
October 2024 (Update)
September 2024 (Update)
July 2024 (Update)
June 2024 (Update)
May 2024 (Update)
April 2024 (Update)
February 2024 (Update)
January 2024 (Update)
December 2023 (Update)
September 2023 (Summary)
High school building pad was completed, concrete footings placed, and a section of sidewalk replaced. Elementary school addition building pad and storm sewer installation is in progress.
On the horizon...
High School Addition
Under slab plumbing and electrical install
Concrete slab on grade placement
Elementary School Addition
Concrete footing placement
Under slab plumbing and electrical install
Concrete slab on grade placement
September 2023
Concrete removal and access road installation has gotten underway at NCEMS, while dirt work for the new addition at NCHS is complete and footings are being poured.
June 2023
February 2023
The bond construction process continues to be in the meeting phases to gather input from staff. The plans for phase 1, new classrooms for grade school and high school, are just about complete and will be submitted for bids soon. The approval of these bids should be at the June 12th board meeting and construction is set to begin in July.
Zach Snethen from HTK, Eric Stallbaumer with AHRS and Tucker Peddicord with Lighthouse Construction met with staff on February 7th to help finalize plans for the first phase of the construction process before they go out for bids. This was the 2nd meeting for the high school science teachers and the primary teachers from the grade school. The group also conducted their first meeting with high school art, band, office staff and special education for the remodeling phase at the high school. The staff input has been very valuable during pre-construction and the meetings will continue throughout the different construction phases. Plans will be shared with the board during their meeting February 13th.
December 2022
For the next few months, the construction for the bond will be in the planning stages. Shovels will hit the ground on June 1st and a great deal of planning will take place before that can happen. Zach Snethen from HTK, Eric Stallbaumer with AHRS and Tucker Peddicord with Lighthouse Construction, met with administration, teachers, Amy Sudbeck #115 BOE and Steve Rothers to begin discussion on the layout of the classrooms and building infrastructure. Input will continue to be gathered so that bids can be requested and submitted. Survey crews have also been busy identifying underground lines.
Staff from the Elementary discussing the Pre K, TK and Kindergarten classrooms.
High School science teachers giving their input about the new classrooms.